Finished Snorkel, Installed Baffle seals, Installed control cables

 

Installed the alternate air door in the snorkel.

 

Formed the right air ramp cone and the cone in the air filter cover and installed them.

 

Installed the baffle seals.

 

Installed ignition wire pass-throughs, the blast tubes for cooling the mag/ignition, and sealed the baffles to the engine case with RTV.

 

Clamped the clamping strips in place on the lower cowl air inlets and filled the gaps with flox.

 

Installed the throttle, prop, mixture and alternate air control cables.

 

Today’s Time (hours): 20.0
Finish kit (hours): 313.0
Total Time (hours): 1047.0

Installed heater control cables

I ran out of heat shrink labels. So wiring came to a halt. I decided to install the cabin heat control cables yesterday. I figured it would be easier while the fuselage is still on its side.

 

I ran the pitot, AOA, and static lines through holes I drilled in the sub panel.

img_4571

 

This evening, I reinstalled the radio racks and instrument panel in preparation for wiring the GDU’s, G5, and panel switches.

img_4572

 

Today’s Time (hours): 4.0
Firewall Forward (hours): 4.0
Total Time (hours): 872.0